Zoo to Paoli Electric Upgrades

Program Status

In Construction and Planning 

Benefits

  • Improves service reliability for Amtrak and SEPTA customers
  • Increases power and efficiency along a critical segment of the Harrisburg Line
  • Replaces aging and inaccessible transmission lines that are not currently on Amtrak property
  • Upgrades Bryn Mawr Substation to a modern traction power system

Estimated Construction Completion

2035

Latest Milestone

Awarded contract for the Bryn Mawr Substation

Hosted public meeting on June 16, 2026

Funding Sources

SEPTA, PennDOT, Amtrak, Submitting for Federal-State Partnership Grant through the FRA

Program Partners

U.S. DOT Federal Railroad Administration (FRA), SEPTA, PennDOT, Philadelphia Electric Company (PECO), local municipalities and counties along the project corridor

The Zoo to Paoli Electrification Transmission Line Project will upgrade the electrification system along 18 miles of Amtrak’s Harrisburg Line in Pennsylvania between Zoo Substation in Philadelphia and Paoli Substation in Chester County.

The Zoo to Paoli multi-year program will advance major power system upgrades along a critical segment of the Harrisburg line increasing service reliability for Amtrak and SEPTA customers. As owner of the Harrisburg line, Amtrak is working with its partners to advance the Zoo to Paoli Electrification Transmission Line Project.  The overall program covers multiple components, including the construction of a new substation, the replacement of aged catenary structures (overhead wires used to supply electricity to a train), the construction of new transmission lines, and upgrades to the signal power system.

Once this project is complete, Amtrak’s Keystone Service and Pennsylvanian trains, as well as the SEPTA Paoli Thorndale Line, will benefit from more reliable service thanks to a modern overhead catenary system (OCS) and increased capacity signal power for future signal upgrades. The existing high voltage transmission line (138kV) located off Amtrak’s right-of-way will no longer be in use as Amtrak will have the new transmission line on Amtrak property to access for maintenance, use and overall increase in system reliability.

Planning and public engagement for this project began in 2012 in accordance with the National Environmental Policy Act (NEPA). An Environmental Assessment (EA) was completed and signed by the Federal Railroad Administration in March of 2017.

Amtrak is working with its partners at the U.S. Department of Transportation, Federal Railroad Administration (FRA), PennDOT, SEPTA, and Philadelphia Electric Company (PECO) as well as local municipalities and counties along the project corridor.

This work will be completed across three major components.

Infrastructure Upgrades

Bryn Mawr Substation

The existing Bryn Mawr Substation adjacent to Bryn Mawr train station (on Bryn Mawr Avenue in Montgomery County) will be demolished and upgraded to a new substation; equipment to reinforce the power supply for the Philadelphia-Paoli route will be added to ease maintenance by consolidating infrastructure on the right-of-way. A contract has been awarded for this project and construction began in the fourth quarter of 2024.

This work will include:

  • removal of existing substation equipment structures
  • demolition of control house building
  • expansion of the substation footprint that is all on Amtrak-owned property
  • installation of new equipment that will increase the capabilities of the Bryn Mawr Substation
  • installation of a brick facade, control building and a signal frequency converter hut

Also included are auxiliary power systems, cabling, feeders, lighting, lightning protection, ground grid, grounding wiring and terminations, fencing, civil works, SCADA and all associated steel structures gantries.

Approximately ten miles of Amtrak right-of-way will be upgraded with new OCS structures carrying a new 138kV transmission and upgraded 6.9kV signal power system. Amtrak initiated procurement for this segment in 2024 and construction is expected to begin in 2025.

Approximately eight miles of Amtrak right-of-way will be upgraded with new OCS structures carrying a new 138kV transmission and upgraded 6.9kV signal power system. Procurement is planned to kick off for this segment in 2028-2029.

Program Benefits

Amtrak’s mission is to provide efficient and effective intercity passenger rail mobility consisting of high-quality service that is trip-time competitive with other travel options. Zoo to Paoli Electric Upgrades will fulfill this mission by delivering the following benefits:  

Service Reliability

Reduced Travel Times and Improved On-Time Performance: The section between Zoo and Paoli is 20 miles long. Existing trains operated by Amtrak and SEPTA experience low-voltage conditions in this section of railroad during periods of higher train density, causing disruptions to rail service. The new Bryn Mawr substation will solve this problem.

Infrastructure: The heights of the proposed structures are a result of meeting both Amtrak’s design requirements and the requirements of the National Electric Safety Code. In order to accommodate the new transmission lines, the new poles will be the minimum height necessary to meet those clearances.

Additional height is needed for structures to provide required clearances at bridges and other crossings.

Service and Community Impacts

All construction activities will be limited to within Amtrak’s right-of-way, and no private property will be impacted. Amtrak is working with SEPTA to minimize impacts to passengers as this and other Amtrak and SEPTA improvement projects continue along the corridor. Furthermore, no street detours or closures are planned.

Thirty-one parking spaces will be impacted by construction at the Bryn Mawr station parking lot. Nineteen will be temporary and twelve will be permanent loss for the new footprint of the substation. There will also be additional truck traffic on local streets during construction, due to equipment delivery and construction activities.

Latest Updates

Amtrak and Partners Break Ground on New Train Maintenance Facility in New York City

August 28, 2026

Amtrak and Partners Break Ground on New Train Maintenance Facility in New York City

The post Amtrak and Partners Break Ground on New Train Maintenance Facility in New York City appeared first on Amtrak...

Amtrak Awarded Nearly $3B in USDOT Grants to Buy New Trains and Improve Service Nationwide

August 14, 2026

Amtrak Awarded Nearly $3B in USDOT Grants to Buy New Trains and Improve Service Nationwide

The post Amtrak Awarded Nearly $3B in USDOT Grants to Buy New Trains and Improve Service Nationwide appeared first on...

Special Weekend Train Schedules Planned for WALK Bridge Construction: Major Reductions to Train Service Between Stamford and New Haven Planned for Select Weekends Beginning September 12

August 13, 2026

Special Weekend Train Schedules Planned for WALK Bridge Construction: Major Reductions to Train Service Between Stamford and New Haven Planned for Select Weekends Beginning September 12

The post Special Weekend Train Schedules Planned for WALK Bridge Construction: Major Reductions to Train Service Between Stamford and New...

Amtrak Awards Contracts and Prepares to Begin Major Dock Bridge Rehabilitation Project

July 28, 2026

Amtrak Awards Contracts and Prepares to Begin Major Dock Bridge Rehabilitation Project

The post Amtrak Awards Contracts and Prepares to Begin Major Dock Bridge Rehabilitation Project appeared first on Amtrak Media.

Amtrak Advances Major Construction Activities for the  B&P Tunnel Replacement Program and Identifies Optimization Opportunities in Coordination with FRA

July 28, 2026

Amtrak Advances Major Construction Activities for the B&P Tunnel Replacement Program and Identifies Optimization Opportunities in Coordination with FRA

The post Amtrak Advances Major Construction Activities for the B&P Tunnel Replacement Program and Identifies Optimization Opportunities in Coordination with...

Joint Statement from Amtrak President Roger Harris and NJ TRANSIT President & CEO Kris Kolluri

June 26, 2026

Joint Statement from Amtrak President Roger Harris and NJ TRANSIT President & CEO Kris Kolluri

The post Joint Statement from Amtrak President Roger Harris and NJ TRANSIT President & CEO Kris Kolluri appeared first on...

Amtrak Celebrates Two South Carolina Station Restorations

March 13, 2026

Amtrak Celebrates Two South Carolina Station Restorations

The post Amtrak Celebrates Two South Carolina Station Restorations appeared first on Amtrak Media.

NJ TRANSIT and Amtrak Prepare to Open First Track on New Portal North Bridge

March 12, 2026

NJ TRANSIT and Amtrak Prepare to Open First Track on New Portal North Bridge

The post NJ TRANSIT and Amtrak Prepare to Open First Track on New Portal North Bridge appeared first on Amtrak...

Amtrak to Launch First Round of Community Grants for the B&P Tunnel Replacement Program on March 23

March 4, 2026

Amtrak to Launch First Round of Community Grants for the B&P Tunnel Replacement Program on March 23

The post Amtrak to Launch First Round of Community Grants for the B&P Tunnel Replacement Program on March 23 appeared...

Portal North Bridge Enters Final Phase of Construction as Work Begins to Put First Track into Service

January 15, 2026

Portal North Bridge Enters Final Phase of Construction as Work Begins to Put First Track into Service

The post Portal North Bridge Enters Final Phase of Construction as Work Begins to Put First Track into Service appeared...

VIDEO: Amtrak’s Transformative Renovation of Philadelphia’s Gray 30th Street Station

January 8, 2026

VIDEO: Amtrak’s Transformative Renovation of Philadelphia’s Gray 30th Street Station

The post VIDEO: Amtrak’s Transformative Renovation of Philadelphia’s Gray 30th Street Station appeared first on Amtrak Media.

VIDEO: Building the Future of American Passenger Rail

December 19, 2025

VIDEO: Building the Future of American Passenger Rail

The post VIDEO: Building the Future of American Passenger Rail appeared first on Amtrak Media.

Stay in Touch

Email your questions, comments or concerns to the project team at ZTP@amtrak.com.