Susquehanna River Bridge Project
Get the latest project news and updates.
Sign Up For Updates Here

Quick Facts

The construction contract was awarded and the final design is underway.

Customer Benefits

  • Increases passenger rail capacity by replacing the existing 2-track bridge with four total tracks across two new bridges
  • Modernizes rail infrastructure including track, overhead catenary/power and signals
  • Improves reliability and safety
  • Increases train speeds and decreases trip times
  • Eliminates conflicts with maritime traffic
  • Awarded the major construction contract and two supporting contracts in late 2023
  • Summer 2024: Begin remnant pier removal
  • Late 2024: Complete 100% design
  • 2025: Begin major construction

Federal Railroad Administration (FRA), Maryland Department of Transportation Maryland Transit Administration (MDOT MTA)

Construction Manager at Risk: Flatiron/Herzog Joint Venture

Project & Construction Management: AECOM Technical Services

Engineer of Record: HNTB

Fully funded by FRA Federal-State Partnership – NEC Grant Program (Awarded November 2023), State of Maryland, Amtrak

Resources

Amtrak’s Susquehanna River Bridge is a two-track, swing-span rail bridge that was built in 1906. This aging bridge is a bottleneck along a critical link of the Northeast Corridor (NEC), one of the busiest and economically vital transportation systems in the world.

The bridge’s swing span must be opened manually by up to 30 personnel to allow taller marine traffic to pass, which causes disruptions to both rail and marine operations. The outdated design of the existing bridge requires passenger trains to slow down to 90 mph and freight trains to 30 mph or less as they cross over the Susquehanna River with speeds up to 125 mph adjacent to the bridge. Due to the two-track design, trains must reduce speed even further or stop on the bridge when crossing to their final designation. 

The Susquehanna River Bridge Project will replace the existing bridge with two new parallel, fixed-span structures featuring a total of four tracks that will improve capacity, trip time and safety for commuter, freight and intercity passenger rail services. The new structures will allow passenger trains to travel at high speeds on this part of the NEC. The NEPA environmental review for the project has been completed and the advanced design phase began in 2017. Amtrak selected a construction contractor in late 2023 and kicked off the project in the Summer of 2024. This roughly $2.7 billion project is supported by a Fed-State Grant and additional funding by Amtrak and the State of Maryland.

For project updates sign up for our newsletter

Stay in Touch

We’d like to hear from you! If you have any questions, email us at [email protected] or call 844-SUS-RAIL (844-787-7245).