Below is a list of current construction activities. Subscribe below for project updates, and contact the program team with any further questions.
We are committed to delivering this Program with your safety as our top priority.
Beginning on or about March 25th, construction crews will begin demolition activities behind the 600 block of N Pulaski St within a fenced area. During this time, residents and businesses may experience temporary noise and dust in the area. Crews will work to minimize disruptions whenever possible.
Contractors will continue mobilizing to conduct site work along N Warwick Ave between W Lexington St and W Franklin St. Please note that this work will occur in multiple areas both west and east of Warwick Ave. Activities include installing fencing, delivering materials, and performing pile driving. No traffic impacts are expected as a result of this work at this time; however, residents may experience increased noise and construction crews in the area.
Beginning in late March, contractors will survey utilities in preparation for upcoming utility relocations at the intersection of W North Ave and Pennsylvania Ave, as well as along I-83 between Exits 5 and 7. These activities will result in lane modifications and detours. Please follow all posted signage while crews complete this work.
Clearing and grubbing along N Warwick Ave between W Lexington St and W Franklin St
Contractors are currently working on the 900 block of N Payson St. This work is a continuation of activities already underway behind the 900 block, which currently includes utility work. To complete this vital work and advance the project, crews have closed N Payson St between W Lafayette Ave and Mosher St. Contractors have installed sound barriers to help reduce construction noise impacts to the surrounding area. Please adhere to all posted no parking signage.
Contractors have started waterline replacement work and have temporarily closed the 700 block of N Payson St to continue essential utility relocations needed for the project to move forward.
Residents can expect:
Crews continue early mobilization activities in the 1000 block of N Payson St to support upcoming work. This advance work is being completed to help progress the overall construction schedule. Activities may include staging of materials, equipment mobilization, installation of fencing and sound barriers, and general site preparation.
Crews continue to perform construction activities along McMechen St near the MTA Light Rail station. This utility relocation work is in preparation for the tunnel’s future north portal and ventilation facility. This work includes roadway utility excavation and installation.
Users can expect:
Crews have begun streetlight relocation work along N Brice St between W Lafayette Ave and W Lanvale St. Following the streetlight work, crews will restore sidewalks, curbs, and pavement impacted by construction. Residents can expect noise, dust, and increased construction activity in the area. Expect parking restrictions and pedestrian detours. Please follow posted signage and use caution when traveling through the area.
To control stormwater flows leaving the construction site, contractors have installed temporary asphalt berms near the intersection of Harlem Ave and N Pulaski St. Drivers are advised to slow travel speeds as they move along these roads.
Crews are continuing work on the utility siphon – a small tunnel that will relocate existing utilities under the existing Amtrak Northeast Corridor railroad tracks.
We will provide detour signage and/or flaggers to indicate any traffic modifications and help motorists and pedestrians navigate through construction areas
PLEASE NOTE:
Crews will generally work Monday through Saturday from 7:00am to 5:00pm unless working extended hours. There may be times when crews will work outside of daytime hours in order to maintain the project schedule. Construction activities are subject to change, and modifications to the schedule may become necessary due to weather delays or other unforeseen conditions. Please use caution when traveling in construction areas.
Amtrak is committed to keeping you informed and providing you with updates regarding construction activities related to the Frederick Douglass Tunnel Program that may impact your neighborhood.
You may have recently noticed work crews in your community. They are conducting soil borings across the Program alignment as a continuation of our pre-construction activities for the Frederick Douglass Tunnel Program.
Here’s What to Expect
Why This Work is Needed
The soil boring process is a pre-construction activity that involves the use of a drill rig drilling a hole into the ground to retrieve a soil sample, which is tested to determine how suitable the soil is for construction.
Questions
For additional information on the Frederick Douglass Tunnel Program please email us at FDTunnel@Amtrak.com or call 443-423-1115.
The Frederick Douglass Tunnel Program will modernize and transform a 10-mile section of the Northeast Corridor to improve rail service reliability, reduce travel times, and support economic and community development in West Baltimore.
The acquisition of properties for the construction of the Frederick Douglass Tunnel Program (Program) began in 2023. In total, 47 properties (residential and commercial) will be demolished. Starting in Spring 2024, demolition contractors K&K Adams and Delaware Cornerstone Builders began to demolish acquired properties to support Program construction.
Here’s What to Expect
Contractor crews will mobilize demolition machinery and install fencing lined with screening fabric around sites to be demolished. Each site may take approximately two to three weeks to complete but the timelines vary depending on unique site conditions, weather, and any unexpected site discoveries. Typical work hours are Monday through Saturday 8am to 5pm with the possibility of Sunday work if needed. Both contractors have secured approved areas for their equipment to be stored at night.
Important Information Related to the Demolition Work
The contractors are experienced in performing demolition work and are familiar with all applicable industry standards for safety and the rules and regulations required by OSHA, Maryland Department of the Environment, and the City of Baltimore for these permitted activities. In addition to the actual demolition work, each contractor will:
Each contractor has a detailed workplan for each group of properties to be demolished, including how adjacent properties will be protected during this process. After demolition is complete, the contractors will install permanent fencing.
Questions
For additional information on the Frederick Douglass Tunnel Program please visit our website fdtunnel.com, email us at FDTunnel@Amtrak.com, or call 443-423-1115.
2026
2025
12.21.2025 & 01.04.2026 Construction Updates
12.07.2025 Construction Updates
11.23.2025 Construction Updates
11.09.2025 Construction Updates
10.12.2025 Construction Updates
09.28.2025 Construction Updates
09.14.2025 Construction Updates
09.01.2025 Construction Updates
08.10.2025 Construction Updates
07.27.2025 Construction Updates
07.13.2025 Construction Updates
07.01.2025 Construction Updates
06.15.2025 Construction Updates
06.01.2025 Construction Updates
05.18.2025 Construction Updates
05.04.2025 Construction Updates
04.20.2025 Construction Updates
04.06.2025 Construction Updates
03.23.2025 Construction Updates
03.09.2025 Construction Updates
02.23.2025 Construction Updates
02.09.2025 Construction Updates
01.26.2025 Construction Updates
01.12.2025 Construction Updates
2024
12.02.2024 Construction Updates
11.11.2024 Construction Updates
10.28.2024 Construction Updates
10.14.2024 Construction Updates
10.07.2024 Construction Updates
09.23.2024 Construction Updates
07.10.2024 Construction Updates
2023
For additional information, email bptunnel@amtrak.com or call (443) 423-1115 to speak to a member of the Program team.
This Website Uses Cookies
Amtrak New Era uses cookies and other tracking technologies to enhance your experience, provide personalized content and ads, and analyze our traffic. These cookies may be set by us or by third-party partners. Non-essential cookies will only be used if you give your consent. You can manage your preferences at any time through the Cookie Settings link. If you are a California resident, you have the right to opt out of the sale or sharing of your personal information. Selecting "Decline All" will opt you out of non-essential cookies and any such data sharing. To learn more, please see our Privacy Policy.