November 7, 2025
Amtrak Celebrates Upgrades at Wisconsin Stations
Customers benefit from $11 million in federal investments COLUMBUS and TOMAH, Wisc. – Amtrak passengers have a more accessible experience...
We achieved back-to-back all-time records in ridership and revenue all while making historic levels of investments to upgrade America’s trains, bridges, tunnels, tracks, signals and electric systems- bolstering America’s growing rail supply chain.
November 7, 2025
Customers benefit from $11 million in federal investments COLUMBUS and TOMAH, Wisc. – Amtrak passengers have a more accessible experience...

November 6, 2025
The post Amtrak and Partners Break Ground on Southampton Rail Yard Modernization Project in Boston appeared first on Amtrak Media.

November 5, 2025
The post Amtrak and Partners Break Ground on Ivy City Rail Yard Modernization Project in Washington, D.C. appeared first on...
October 30, 2025
WASHINGTON, D.C. – U.S. Department of Transportation (USDOT) Secretary Sean P. Duffy announced today that the Department has reached three...
October 27, 2025
The post WATCH: Connecticut River Bridge Project appeared first on Amtrak Media.
October 22, 2025
The post From Pueblo to the Northeast: Airo Fleet Moves Toward Debut appeared first on Amtrak Media.
October 17, 2025
Customers benefit from $30 million federal investment statewide DEVILS LAKE and FARGO, N.D. – Amtrak passengers have a more accessible...

October 15, 2025
B&P Tunnel Replacement ProgramConstruction Updates US-40 Construction Area Traffic Map Subscribe for Email Updates Construction Area Traffic Map Intersection of N Warwick St & W Franklin St Intersection of W Franklin & Wheeler Intersection of N Smallwood btwn W Mulberry & W Franklin W Franklin at N Payson, N Brice & N Payson Streets West […]

September 16, 2025
The project remains on schedule for train service to resume in the fully rehabilitated Line 2 tunnel in July 2026.
August 28, 2025
Construction to begin by the end of 2027 NEW YORK – The U.S. Department of Transportation (USDOT) and Amtrak have...

August 27, 2025
Completely rehabilitating a 115-year-old tunnel is a massive undertaking. During the decommissioning phase earlier this summer, we removed approximately 24,000 linear feet of running rail, 12,000 linear feet of 3rd rail, 8,000 railroad ties, and 8,000 cubic yards of ballast.
August 27, 2025
The post Amtrak Makes History Launching NextGen Acela Service appeared first on Amtrak Media.

August 21, 2025
With “America250” fast approaching – a celebration of 250 years since the signing of the Declaration of Independence – this work is an important opportunity to reflect on our nation’s past, honor the contributions of Americans, and look toward the future.

August 19, 2025
The post Amtrak Advances Three Major East Coast Rail Yard Modernization Projects appeared first on Amtrak Media.

August 13, 2025
August brought significant momentum to the East River Tunnel Rehab project with the start of major bench wall demolition. Originally built in the early 1900s, these 6-foot-tall structures line both sides of the tunnel, providing critical emergency egress for passengers in the event of a major emergency.

July 29, 2025
Since our last update earlier this month, the project team has continued to remove ballast from the tunnel and conduct other demolition work needed to remove everything down to the tunnel liner.

July 24, 2025
This week, we shared a look at the first new Amtrak Airo trainset to ship from Siemens' Sacramento facility to Pueblo, CO for testing.

July 17, 2025
Since the start of the long-term outage on May 23, the East River Tunnel Rehab Project has been steadily advancing through early, high-impact milestones. As detailed in past updates, we worked with our contractor to complete all decommissioning tasks followed by safely removing all assets from within the tunnel, clearing the way for major demolition activities.

July 11, 2025
Work recently wrapped up to decommission existing tunnel systems (i.e. power and signaling) and install temporary systems (i.e. power, lighting, and ventilation fans). The temporary systems are key to supporting work in the first tunnel (Line 2) over the next year.

June 27, 2025
This week marks one month since the long-term outage began for the East River Tunnel Rehab Project. The project is advancing on schedule, and to date there have been no significant unplanned service issues in the three remaining operational tunnel tubes affecting impacted Amtrak, LIRR, and NJT customers.

June 17, 2025
Amtrak Acting Senior Vice President of Capital Delivery Jim Short recently visited the East River Tunnel Rehab Project site for a first-hand look at the progress made by Amtrak and our contractor over the first few weeks of the long-term outage.

June 10, 2025
“Decommission” is now the word of the week. Before demolishing the existing tunnel systems in the 1st tunnel (Line 2) down to the concrete liner, the project team must decommission – or power off and remove from service – all the existing tunnel systems.

June 6, 2025
On Thursday, May 29, Amtrak joined Baltimore City Councilman John T. Bullock, community members from the Greater Rosemont and Midtown Edmondson neighborhoods, and several media outlets to kick off a new Historic Salvage Program at the historic Atlas Building on Edmondson Avenue.

June 3, 2025
On Monday, the project team successfully transitioned work into Line 2, right on schedule.

May 27, 2025
Over the weekend, Amtrak crews kicked off the first long-term track outage in support of the East River Tunnel Rehabilitation Project (ERT Rehab), a critical infrastructure investment that will restore the two tunnel tubes damaged by Superstorm Sandy (Line 1 & Line 2). This is Amtrak’s largest planned outage in recent history, an important undertaking planned in coordination with our partners over several years.