Below is a list of current construction activities for the Frederick Douglass Tunnel Program. Subscribe below for project updates, and contact the program team with any further questions.
Clearing and Grubbing
Contractors will clear and remove vegetation such as trees, shrubs and brush, roots, stumps, and other materials to provide a solid base and better visibility – preparing the area for site work to begin in new areas. Work can be expected to:
Early Mobilization for Utility Siphon Tunnel
Starting in early April, crews will mobilize on the 800 block of Spedden Street in preparation for construction of a utility siphon – a small tunnel – that will relocate existing utilities under the existing Amtrak Northeast corridor railroad tracks.
Test Blasting
Starting in mid-April, crews will begin preparing for the drill and blast operations to excavate for the utility siphon tunnel. The contractors will complete small, controlled test blasts to along Pulaski St to confirm work operates as designed.
Pile Driving and Excavation
This week, crews will begin installing steel sheet pilings that support the areas being excavated (dug) for upcoming utility relocations, weather permitting.
Ongoing Activities
Crews continue to survey the area, complete preconstruction inspections, install instrumentation and monitoring devices, complete utility investigations and work in manholes throughout the project area. Work continues on N Pulaski, W Lanvale, and N Brice Streets.
Crews continue to install water lines along N. Payson and N. Pulaski Streets
Impacted residents will receive additional notification prior to any expected water shut offs.
Traffic Modifications
Amtrak is committed to conducting this work in a manner that is least disruptive to the community. For your safety, we ask that you please keep all children and pets away from the construction area.
During construction, you can expect:
PLEASE NOTE:
Crews generally work Monday through Friday from 7:00am to 5:00pm, weather permitting. Construction activities are subject to change and modifications to the schedule may become necessary due to weather delays or other unforeseen conditions. Please use caution when traveling in construction areas.
Amtrak is committed to keeping you informed and providing you with updates regarding construction activities related to the Frederick Douglass Tunnel Program that may impact your neighborhood.
You may have recently noticed work crews in your community. They are conducting soil borings across the Program alignment as a continuation of our pre-construction activities for the Frederick Douglass Tunnel Program.
Here’s What to Expect
Why This Work is Needed
The soil boring process is a pre-construction activity that involves the use of a drill rig drilling a hole into the ground to retrieve a soil sample, which is tested to determine how suitable the soil is for construction.
Questions
For additional information on the Frederick Douglass Tunnel Program please email us at [email protected] or call 443-423-1115.
The Frederick Douglass Tunnel Program will modernize and transform a 10-mile section of the Northeast Corridor to improve rail service reliability, reduce travel times, and support economic and community development in West Baltimore.
The acquisition of properties for the construction of the Frederick Douglass Tunnel Program (Program) began in 2023. In total, 47 properties (residential and commercial) will be demolished. Starting in Spring 2024, demolition contractors K&K Adams and Delaware Cornerstone Builders began to demolish acquired properties to support Program construction.
Here’s What to Expect
Contractor crews will mobilize demolition machinery and install fencing lined with screening fabric around sites to be demolished. Each site may take approximately two to three weeks to complete but the timelines vary depending on unique site conditions, weather, and any unexpected site discoveries. Typical work hours are Monday through Saturday 8am to 5pm with the possibility of Sunday work if needed. Both contractors have secured approved areas for their equipment to be stored at night.
Important Information Related to the Demolition Work
The contractors are experienced in performing demolition work and are familiar with all applicable industry standards for safety and the rules and regulations required by OSHA, Maryland Department of the Environment, and the City of Baltimore for these permitted activities. In addition to the actual demolition work, each contractor will:
Each contractor has a detailed workplan for each group of properties to be demolished, including how adjacent properties will be protected during this process. After demolition is complete, the contractors will install permanent fencing.
Questions
For additional information on the Frederick Douglass Tunnel Program please visit our website fdtunnel.com, email us at [email protected], or call 443-423-1115.
2025
04.06.2025 Construction Updates
03.23.2025 Construction Updates
03.09.2025 Construction Updates
02.23.2025 Construction Updates
02.09.2025 Construction Updates
01.26.2025 Construction Updates
01.12.2025 Construction Updates
2024
12.02.2024 Construction Updates
11.11.2024 Construction Updates
10.28.2024 Construction Updates
10.14.2024 Construction Updates
10.07.2024 Construction Updates
09.23.2024 Construction Updates
07.10.2024 Construction Updates
2023
For additional information about the Frederick Douglass Tunnel Program, email [email protected] or call (443) 423-1115 to speak to a member of the program team.