November 22, 2026
We are committed to delivering this Program with your safety as our top priority.
To maintain progress on this critical program, weekend work will occur across the project area in the coming weeks. Residents may notice increased construction activity during these times.
Upcoming Activities
Utility Surveys
Contractors will be conducting utility surveys in preparation for upcoming utility relocations at the intersection of W North Ave and Pennsylvania Ave, as well as along I-83 between Exit 5 (Maryland Ave) and Exit 7 (28th St/Druid Park Lake Dr). These activities may require temporary lane modifications and detours. Survey activities are anticipated to begin in late 2026, with additional details to be shared as work progresses.
Completed Activities
- First phase of pile driving activities along N Pulaski St, between W Lafayette Ave and Harlem Ave have been completed. Other major construction activities will continue throughout the area.
- First phase of pile driving activities behind the 800 block of Spedden St have been completed. Other major construction activities will continue throughout the area.
Ongoing Activities
Laurens St Early Work
Contractors continue to install fencing near the intersection of Laurens St and N Fulton Ave and the intersection of Laurens St and N Monroe St. This work will help establish a defined work zone and support upcoming program operations in the area.
Residents may notice:
• Increased equipment in the area
• Intermittent activity during installation
Construction Behind N Payson St
Construction activities are ongoing behind the west side of the 900 block of N Payson St as part of the B&P Tunnel Replacement Program. A variety of construction activities are taking place in this area, including mass excavation and utility relocations as well as overnight work from 5:00 PM to 2:00 AM.
Residents may notice:
• Increased construction activity during daytime and overnight hours
• Increased large truck traffic entering and exiting the worksite
• Worksite lighting to support safe operations during nighttime activities
Waterline Work at N Payson St & W Lafayette Ave
Waterline work is ongoing at the intersection of N Payson St and W Lafayette Ave, requiring a partial closure of the intersection. Temporary traffic changes remain in place to safely accommodate construction activities while maintaining pedestrian access through the area.
Residents and road users can expect:
• Temporary lane closures, with two-way traffic maintained
• Traffic delays while traveling through the work zone
• Pedestrian detours and temporary sidewalk impacts
• Increased construction equipment and activity in the area
• Temporary parking restrictions
Please follow all posted ‘No Parking’ signage and use caution while traveling through the work area.
W North Ave Traffic Impacts
Manhole work is ongoing at the intersection of W North Ave and McMechen St as part of utility work in the area. The work requires temporary traffic adjustments to accommodate construction activities.
Residents and road users can expect:
• Temporary lane closures and traffic restrictions
• Traffic delays while traveling through the work zone
• Temporary pedestrian detours and sidewalk impacts
Please follow all posted traffic and parking signage and use caution when traveling through the work area.
W Franklin St Monopole Work
Amtrak is using a portion of the American Ice Company property at 2100 W Franklin St to provide additional construction access for crews. Contractors are using the access road to support construction of temporary overhead power lines at the rear of the property as part of the broader B&P Tunnel program.
Construction activities may include:
• Increased construction activity behind 2100 W Franklin St
• Temporary changes to traffic patterns on W Franklin St
Please use caution while traveling through the area and follow posted signage.
Price Busters Sidewalk Impacts
Construction activities are ongoing outside of Price Busters at 2415 W Franklin St. Contractors are continuing sidewalk removal in preparation for upcoming construction activities in the area.
Residents may notice:
• Temporary sidewalk closure outside of Price Busters
• Pedestrian detours with clearly marked signage
• Increased construction equipment and activity in the area
N Warwick Ave Activities
Contractors will continue mobilizing to conduct site work along N Warwick Ave between W Lexington St and W Franklin St. Please note that this work will occur in multiple areas both west and east of Warwick Ave. Activities include delivering materials, pile driving, and fencing installation.
Residents and road users can expect:
• Lane closures, traffic pattern shifts, and flaggers on N Warwick Ave
• Noise from heavy equipment
• Construction crews working on site and in nearby areas
• Weekend work as needed
McMechen St Activities
Crews continue to perform construction activities along McMechen St near the MTA Light Rail station. This utility relocation work is in preparation for the tunnel’s future north portal and ventilation facility. This work includes roadway utility excavation and installation.
Road users can expect:
• Lane closures, traffic pattern shifts, and flaggers on McMechen St and W North Ave
• Heavy equipment and construction crews working on site
• Noise, dust, and debris associated with demolition, excavation, and utility installation
Erosion and Sediment Controls
To control stormwater flows leaving the construction site, contractors have installed temporary asphalt berms near the intersection of Harlem Ave and N Pulaski St. Drivers are advised to slow travel speeds as they move along these roads.
Other Construction Activities
Work continues on N Pulaski St, W Lanvale St, W Lexington Ave, W North Ave, N Brice St, McMechen St, W Mulberry St, N Warwick Ave, and W Franklin St, primarily within fenced areas. While much of the activity is not immediately visible to the community, crews remain active throughout these construction zones.
Ongoing Road Closures
• Full road closure of N Pulaski St between W Lafayette Ave and Harlem Ave
• Full road closure of W Mulberry St between N Warwick Ave and N Smallwood St
• Full road closure of N Payson St between W Lanvale St and Rayner Ave
We will provide detour signage and/or flaggers to indicate any traffic modifications and help motorists and pedestrians navigate through construction areas.
PLEASE NOTE:
Crews will generally work Monday through Saturday from 7:00am to 5:00pm unless working extended hours. There may be times when crews will work outside of daytime hours in order to maintain the project schedule. Construction activities are subject to change, and modifications to the schedule may become necessary due to weather delays or other unforeseen conditions. Please use caution when traveling in construction areas.